Gullivers Park Roundabout Design

OCSC were appointed by the Cosgrave Group to complete the design of a new access roundabout in to the existing Gulliver Retail Park in Santry. The scheme is located on Northwood Avenue and the roundabout was to replace an existing priority tee junction into the Retail Park so as to provide increased access capacity.

The project involved the planning, design and construction of a roundabout, a new pelican crossing, bus stops and a surface overlay of a section of Northwood Avenue.

The scheme was to be completed with live traffic so that a challenging Traffic Management Plan had to be developed by OCSC in order to maintain activity within the overall mixed use campus. The scheme was taken from planning through detail design and was completed within three months. The bulk of the schemeĀ  involved the construction of the roundabout, pelican crossing, bus stops, public lighting, utilities and other associated works.

OCSC provided planning, design, contract documentation, contract administration and site supervision services for the project.